Plastics Manufacturing Plant Upgrade
Interior Excavated Pit 120' x 12' x 8'
Checkerboard Pours
Using 8,000 psi High Early Concrete
Concrete Achieved 3,000 psi in 6 hrs
Our Technique Allowed Us to Strip and Pour Continuously Around-the-Clock.
We Used This Process on the Walls Also.
We Don't Sleep 'Til The Job Gets Done!
Right Foreground Check Shirt, Jack Baker
Subsurface Catchment 5 Days Excavation, Placement and Removal of Sheet Piles, Pouring Concrete Walls and Floor Slabs.
Three Safety Professionals 24/7, one was
Plant Provided, General Contractor's + Our Own Safety Officer Ensured Job Safety.
Temporary Surrounds Removed, Sides Filled Capped Subsurface Machinery Catchment Pit
Start to Finish (Sun-Thurs) 5 days